Logung Dam construction to be completed in September
Senin, 19 Maret 2018 10:35 WIB
Logung Dam located in Kudus Regency, C. Java. (Photo: Akhmad Nazaruddin Lathif)
Kudus (Antaranews Jateng) - Construction of the Logung dam in Kudus, Central Java, is to be completed in September this year, a project leader said.
Plan to finish the construction in 2017 or earlier than schedule failed mainly on too much rain hampering works, the project leader Dodi Indrawan said here on Sunday.
"So far completion is 85 percent that we can expected to finish the project in September this year," Dodi said.
He said currently the workers are piling earth to build the dam when there is no rain.
"We could not build a dam when there is rain unless we cover the dam with plastic," he added.
The workers also are building the spillway , he said, adding, when the wall has been built and construction of the spillway has been completed, the reservoir would be filled with water from the river.
He said it would take a season to fill the dam with water, adding so far no problem other than rain hampering the process of building the dam.
The dam would benefit the local people as it would better guarantee irrigation and help prevent flooding in rainy days.
Earlier villagers rejected the construction of the dam in their farm lands. They case even was brought to court but the dispute was finally settled with a compromise.
The project costs around Rp604.15 billion with fund from the state budget.
Plan to finish the construction in 2017 or earlier than schedule failed mainly on too much rain hampering works, the project leader Dodi Indrawan said here on Sunday.
"So far completion is 85 percent that we can expected to finish the project in September this year," Dodi said.
He said currently the workers are piling earth to build the dam when there is no rain.
"We could not build a dam when there is rain unless we cover the dam with plastic," he added.
The workers also are building the spillway , he said, adding, when the wall has been built and construction of the spillway has been completed, the reservoir would be filled with water from the river.
He said it would take a season to fill the dam with water, adding so far no problem other than rain hampering the process of building the dam.
The dam would benefit the local people as it would better guarantee irrigation and help prevent flooding in rainy days.
Earlier villagers rejected the construction of the dam in their farm lands. They case even was brought to court but the dispute was finally settled with a compromise.
The project costs around Rp604.15 billion with fund from the state budget.
Pewarta : Akhmad Nazaruddin Lathief
Editor : Achmad Zaenal M
Copyright © ANTARA 2026
Terkait
Kantor Pertanahan Blora pastikan hak pemilik lahan untuk pembangunan Bendungan Cabean
13 November 2025 8:55 WIB
Bhabinkamtibmas Bendungan Wonosobo sambangi peternak, cegah penyakit mulut dan kuku
13 January 2025 7:59 WIB, 2025
Pemanfaatan air baku Bendungan Logung untuk PDAM Kudus tunggu bantuan pusat
18 December 2024 19:39 WIB, 2024
5.000 hektare sawah dapat pasokan air irigasi Bendungan Logung Kudus
10 October 2024 13:31 WIB, 2024
Petani manfaatkan pengairan irigasi dari Bendungan Logung yang telah selesai dibangun Kementerian PUPR
26 July 2024 16:58 WIB, 2024
Terpopuler - ENGLISH
Lihat Juga
Blora District Police vow firm action following fatal fire at illegal oil well
18 August 2025 17:25 WIB
Culture minister launches Pramoedya's centenary festival in Blora, Central Java
11 February 2025 11:05 WIB, 2025
Minister Zulkifli calls for upgraded quarantine systems in Indonesia
16 January 2025 15:55 WIB, 2025
Deputy Minister Giring Ganesha seeks youngsters' help to preserve batik
06 January 2025 5:11 WIB, 2025