Logung Dam Project in Kudus 58 Percent Completed
Rabu, 13 September 2017 18:17 WIB
Logung Dam project. (ANTARA FOTO/Yusuf Nugroho)
Kudus, ANTARA JATENG - Construction of the Logung dam in the district of Kudus, Central Java, has been 58 percent completed and it is expected to be completed in mid 2018.
Project supervisor Dodi Indrawan said here on Wednesday the process of construction has been smooth . There is no more protest from local people against the project, he said.
Currently the project is in the process of piling up the earth to form the dam walls and spillway.
Earlier there had been dispute over the land . Villagers claiming to be the right owners of the land brought the case to court demanding compensation .
The case was settled with the Supreme Court ruling that the district administration paid a compensation of Rp28,000 per square meter to the villagers.
The dam project occupying 196 hectares of land in the villages of Tanjungrejo and Honggosoco in the sub-district of Jekulo, villages of Kandangmas and Rejosari in the sub-district of Dawe and land belonging to state-owned forestry company Perum Perhutani, is estimated to cost Rp604.15 billion.
The government has a target to build 49 dams from 2015 to 2019. The projects included 13 dams in 2015, eight dams in 2016 and nine dams this year.
Project supervisor Dodi Indrawan said here on Wednesday the process of construction has been smooth . There is no more protest from local people against the project, he said.
Currently the project is in the process of piling up the earth to form the dam walls and spillway.
Earlier there had been dispute over the land . Villagers claiming to be the right owners of the land brought the case to court demanding compensation .
The case was settled with the Supreme Court ruling that the district administration paid a compensation of Rp28,000 per square meter to the villagers.
The dam project occupying 196 hectares of land in the villages of Tanjungrejo and Honggosoco in the sub-district of Jekulo, villages of Kandangmas and Rejosari in the sub-district of Dawe and land belonging to state-owned forestry company Perum Perhutani, is estimated to cost Rp604.15 billion.
The government has a target to build 49 dams from 2015 to 2019. The projects included 13 dams in 2015, eight dams in 2016 and nine dams this year.
Pewarta :
Editor :
Copyright © ANTARA 2026
Terkait
Kemenag terbitkan Edaran Pembayaran DAM, Ini tujuan dan besaran biayanya
03 June 2024 17:41 WIB, 2024
Bupati: Sabo dam jadi solusi tanggulangi banjir bandang Wonosoco Kudus
01 December 2023 10:54 WIB, 2023
Terpopuler - ENGLISH
Lihat Juga
Blora District Police vow firm action following fatal fire at illegal oil well
18 August 2025 17:25 WIB
Culture minister launches Pramoedya's centenary festival in Blora, Central Java
11 February 2025 11:05 WIB, 2025
Minister Zulkifli calls for upgraded quarantine systems in Indonesia
16 January 2025 15:55 WIB, 2025
Deputy Minister Giring Ganesha seeks youngsters' help to preserve batik
06 January 2025 5:11 WIB, 2025